ON SITE WORK-SHOPS & SITE ESTABLISHMENT 

On site fabrication workshop for the duration of the project building a fuel tank farm, 60 meters long x 18 meters wide x 9 meters on eaves with 4 x 5 ton overhead cranes .... 
1) Plasma cutter 12 meter bed
2) Plasma cutter 3 meter bed
3) Steel Rollers x 3 x 5mm - 30mm
4) Welding Stores
5) Equipment Stores
6) Welding Machines
Flow of production steel plates arrive through the one side placed onto the plasma cutter to be trimmed and beveled, depending the thickness of the plate it will be moved over to the the respective steel roller, then onto the sandblasting area and onto the paint bay.
placed into there cradles and ready for the site installation process.